Submit a progress claim
Raise a progress claim against one or more Schedule of Values lines for a billing period in Connect web, attach supporting documents, and submit it for assessment.
When to use this
At the end of a billing period — typically monthly — when you've completed work against a subcontract and want to claim against it.
Prerequisites
- Subcontract in Active, PC, DLP, or Final status — see Subcontract states
- Sufficient progress against the SoV to claim (claim lines > $0)
- Supporting documents ready to upload — invoices, photos, timesheets, etc. — where the head contractor requires them
- Signed in to Connect web
Walkthrough
Walkthrough coming
A step-by-step Scribe walkthrough for this task is being recorded. Track its status in the Scribe register (internal).
- In Connect web → Work Orders → open the subcontract you want to claim against.
- Click New Claim (or Submit a Claim).
- Select the Claim Type — Progress, Final, or Retention Release.
- Set the Claim Period — period start and period end (the dates the work covers).
- For each SoV line, enter the Submitted amount this period. You can enter either a dollar amount or a % complete figure — the system calculates the other.
- Attach supporting documents per line where the head contractor requires it (camera-roll uploads work — drag and drop or click to browse).
- Review the totals — gross claimed, retention held this claim, net payable.
- Click Submit.
You'll see a confirmation with:
- Service Date — when the claim was received in the head contractor's system (this is what starts their statutory response clock)
- Assessment Due Date — when the head contractor must respond, per the statutory window for their jurisdiction
You'll also receive a confirmation email with the same details.
What success looks like
- Claim shows in your Claims list with status Submitted.
- You receive a confirmation email with the Service Date, Assessment Due Date, and a summary of the claim.
- The head contractor receives a notification immediately.
- The SoV's Remaining to Claim figures update to reflect the new pending amount.
Gotchas
- You can't claim more than the Available to Claim amount on a line. Over-claiming is blocked at submission with a per-line breakdown of why.
- The Service Date is set automatically and can't be changed. Backdating the Claim Date (the date you put on your claim) doesn't shorten the head contractor's response window — the clock runs from Service Date.
- If the subcontract has Concurrent Claims = false, you can only have one claim in progress at a time. Submit a new one only after the previous one reaches a terminal state (Approved, Billed, or Rejected).
- Rejected claims keep the original Assessment Due Date — rejection doesn't reset the clock, so resubmit quickly.
- You can save a claim as Draft and come back to it. Drafts don't trigger any statutory clock — only Submit does.