The main fields on a Gantt Task record, grouped by purpose. This is a partial reference covering the fields most commonly edited or queried — the full record has roughly 50 fields, most of which are internal bookkeeping.
One of ASAP (default), ALAP, MSO (Must Start On), MFO (Must Finish On), SNET (Start No Earlier Than), SNLT (Start No Later Than), FNET (Finish No Earlier Than), FNLT (Finish No Later Than).
Constraint Date
Paired with the constraint type for hard or bounded dates.
Slack (days)
Free slack. Tasks with zero slack are on the critical path.
The resources allocated to this task (Employees, Vendors, Equipment, Roles or Crews).
Estimate Tasks
When Project Financials is installed, the Estimate items this task rolls cost up to.
Author input needed
The full Gantt Task record has more fields than are surfaced here — integration IDs, hidden phantom IDs, sandbox migration fields, Field Service Management fields and a number of UI-display fields. Most users never touch them. If a deeper reference is needed for advanced reporting, raise the request with the implementation team and this page will be expanded in Phase 5.