Help Center
Home
Get started
FullClarity
Home
Get started
FullClarity
  • Get started
  • Construction for NetSuite
  • Project Financials
    • Project Financials quick start
    • Install & configure Project Financials
    • How to

      • Creating a project
      • Customise terminology (rename records)
        • Estimate columns
        • Budget columns
        • Forecast columns
        • Revenue recognition columns
      • Managing cost centres
      • Estimating

        • Creating an estimate
        • Adding lines to an estimate
        • Importing an estimate from a spreadsheet
        • Creating purchase orders from the estimate
    • Contracts & billing

      • Contracts & billing
      • Set up billing schedules
      • Issue a progress claim
      • Create a variation
    • Revenue recognition

      • Revenue recognition
      • Set up revrec rules
      • Run a monthly batch
      • Adjust a revrec entry
      • Capital project revrec
    • Reference

      • Reference
      • Configuration record fields
      • Permissions
      • Custom records
      • Column glossary
  • Subcontracts
    • For head contractors

      • For head contractors
      • Create a subcontract
      • Approve a subcontract variation
      • Raise a back-charge
      • Assess a subcontractor claim
    • For subcontractors — web

      • For subcontractors — web
      • View your subcontracts
      • Submit a progress claim
      • Manage variations
    • For subcontractors — mobile

      • For subcontractors — mobile
      • Sign in
      • View your work orders
      • Submit a claim with photos
    • Reference

      • Subcontract states
  • Retainage
    • Quick start
    • Install & configure
    • How to

      • Set up retainage on a contract
      • Issue a retainage claim
      • Release retainage at handover
    • Reference

      • Permissions
  • Timeline
    • Quick start
    • Install & configure
    • How to

      • Create a Gantt from a template
      • Add tasks and dependencies
      • Allocate resources
    • Reference

      • Task fields reference
      • Permissions reference
  • Certified Documents
    • Quick start
    • Install & configure
    • How to

      • Set up a document type
      • Request a document from a vendor
      • Approve or reject a submission
    • Reference

      • Permissions reference
  • File Storage
    • Install & configure
    • How to

      • Enable File Storage on a record type
      • Migrate files from the NetSuite File Cabinet
      • Connect your Microsoft 365 / SharePoint
    • Reference

      • Permissions reference
  • Project Storage
    • Install & configure
    • How to

      • Enable the project files subtab
      • Browse files on a project
  • Project Tracker
    • Quick start
    • Install & configure
    • How to

      • Log an issue
      • Add notes to an issue
      • Run UAT
    • Reference

      • Issue fields
      • UAT results & issue states
      • Permissions
  • Portal
    • Install & configure
    • How to

      • Register a NetSuite account with the FullClarity Portal
      • Refresh API credentials
  • Code Library
    • Install & configure
  • AI Integration
    • How to

      • Set up an MCP role for AI access
      • Connect an AI assistant to FullClarity
    • Reference

      • Available MCP tools

Approve a subcontract variation

Review and approve a variation against an existing subcontract, with full delta context — original contract value, prior approved variations, and the specific change up for approval — and let the system amend the linked Purchase Order automatically.

  • When to use this
  • Prerequisites
  • Walkthrough
  • What success looks like
  • Gotchas
  • Related

When to use this

When a subcontractor (or your own project manager) raises a change against an existing subcontract — additional scope, scope reduction, rate change, or defect-driven adjustment — and the variation is now sitting in Pending Approval waiting for your decision.

Prerequisites

  • Subcontract in Signed, Active, PC, or DLP status (variations can't be raised against Draft or Closed) — see Subcontract states
  • The Variation has been created and submitted for approval — variations can come from three places:
    • The New Variation action on the Subcontract record
    • An approved variation cost estimate (fan-out from the estimating side)
    • Cloning an existing variation as a template
  • Permission to approve variations for this subcontract's subsidiary

Walkthrough

Walkthrough coming

A step-by-step Scribe walkthrough for this task is being recorded. Track its status in the Scribe register (internal).

  1. Open the Variation record in Pending Approval status (from the dashboard reminder, an email notification, or the Subcontract's Variations subtab).
  2. Review the delta-context summary at the top of the form. It shows:
    • Original Contract Value — the subcontract value at award
    • Prior approved variations — the running total of variations already approved
    • This variation — the value of the change in front of you
    • Resulting Revised Contract Value — what the contract will become if you approve
  3. Below the summary, review the variation lines — what scope is being added or removed, and the Variance Reason on any line being adjusted.
  4. Click Approve.

On approval, the system:

  • Amends the linked Purchase Order automatically (no manual PO edit)
  • Updates the Subcontract's Revised Contract Value
  • Notifies the subcontractor
  • If the variation is flagged as Pass-Through to Customer Variation, the approval is blocked until the linked customer-side variation is itself approved

What success looks like

  • Variation status changes to Approved, with an approval timestamp and approver name on the record.
  • The Subcontract's Variations subtab shows the variation with its new status.
  • The Purchase Order linked to the subcontract has been amended — you'll see the amended-date stamped on the variation.
  • The Subcontract's Revised Contract Value has updated automatically.
  • The subcontractor sees the new contract value in their Connect view at next sync.
  • The audit trail records the approval and the PO line IDs that changed.

Gotchas

  • Approval is blocked if the variation would push the Revised Contract Value below what has already been claimed and paid — this prevents over-approving deductions.
  • Approval is blocked if the linked Customer Variation isn't yet Approved (pass-through variations only).
  • Approval is blocked if the subcontractor's pre-qualification has expired — administrators can override this with a reason.
  • Rejected variations aren't deleted. They sit on the subcontract in Rejected state and can be re-submitted.
  • Post-approval reversal isn't supported directly. If an approved variation needs to be undone, raise an offsetting variation with a negative value — see Raise a back-charge for the same pattern applied to recoveries.

Related

  • Create a subcontract
  • Assess a subcontractor claim
  • Raise a back-charge